Proposed Construction of Road from Gedong to Kpg. Semalatong
Simunjan, Samarahan Division
Direct Negotiated Contract · PWD/HO/B084/2023
Reporting period 26 Sep – 25 Oct 2026
Progress & QA/QC Meeting No. 33
Contract at a glance
- Project title
- Proposed Construction of Road from Gedong to Kampung Semalatong, Simunjan, Samarahan Division
- Contract no.
- PWD/HO/B084/2023
- Client
- Government of Sarawak
- Superintending Officer
- Jabatan Kerja Raya Samarahan
- Consultant
- Perunding Timur (S) Sdn. Bhd.
- Contractor
- Glumox Abiz Sdn. Bhd.
- Insurance coverage
- 22/12/2023 to 21/06/2028
- DOSH registration no.
- TBA
- Min. interim payment
- RM 1,000.00
- LAD
- 0.0182% of original contract sum
- DLP
- 24 months
A shorter, direct link for Kpg. Semalatong
JKR Sarawak intends to take over and upgrade the existing plantation road from Gedong to Kpg. Semalatong, building a shorter, more direct and efficient link between the two.
The new road lets the people of Kpg. Semalatong reach Gedong, Simunjan and Serian towns to market their agricultural produce, and makes it easier to reach government offices.
Objectives
Shorten the travel distance from Kpg. Semalatong to the Pan Borneo Highway, Serian Town and Gedong.
Provide a safe and reliable road network system.
Ease transport of agricultural produce and logistics, raising the economic and social status of the area in support of the government's efforts to eliminate hardcore poverty.
Project components
Organisation, meetings & personnel
Project consultant team (PTSB)
Project Director
Organisation chart updated as of 25 April 2025.
32 progress & QA/QC meetings held
Registered professionals & supervisors
Professional: any personnel registered with the Board of Engineers Malaysia (BEM), i.e. Chief Resident Engineer, Resident Engineer, Assistant Resident Engineer, Project Manager or Site Engineer.
QA/QC status as of 25 October 2026
Reporting period 26 Sep – 25 Oct 2026
1 site memos
0 tests
0 NCR · 0 RFI
Approval chit requests
By work category (cumulative 986)
Approval chit summary table
| Description | Previous Month | Oct '26 | Total |
|---|---|---|---|
| EARTHWORK / CLEARING / USM | 283 | 0 | 283 |
| Drainage Work | 10 | 0 | 10 |
| Road Work | 2 | 0 | 2 |
| Culvert Work | 13 | 0 | 13 |
| Ground treatment | 240 | 0 | 240 |
| Survey & Setting Out | 48 | 0 | 48 |
| Bridge Work | 78 | 0 | 78 |
| Concrete Work | 69 | 0 | 69 |
| Quality Testing | 241 | 0 | 241 |
| Road Furniture | 2 | 0 | 2 |
| TOTAL | 986 | 0 | 986 |
Material approval
CODE 1 Approved CODE 2 Commented, resubmit CODE 3 Not approved, resubmit
Major works must be at Code 1 before work proceeds on site.
Material approval register (45 items)
| No. | Reference No. | Description | Date Replied | Status / Remarks / Action |
|---|---|---|---|---|
| 1 | PTSB/JKRSMRH/SEMALATONG/2024/002 | Proposed Non-Woven Geotextile Type 1 & 2 | 26/01/2024 | No objection, with comment |
| 2 | PTSB/JKRSMRH/SEMALATONG/2024/004 | Proposed Prefabricated Vertical Drain | 29/02/2024 | No objection |
| 3 | PTSB/JKRSMRH/SEMALATONG/2024/007 | Proposed HDPE Pipe Culvert | 4/03/2024 | No objection, with comment |
| 4 | PTSB/JKRSMRH/SEMALATONG/2024/012 | Test Report for 38mm & 75mm DCR Crushed Aggregate | 12/03/2024 | No objection |
| 5 | PTSB/JKRSMRH/SEMALATONG/2024/013 | Test Report for Sand | 2/04/2024 | No objection, with comment |
| 6 | PTSB/JKRSMRH/SEMALATONG/2024/018 | Proposed Precast 250mmx250mm RCSQ Pile | 7/05/2024 | No objection |
| 7 | PTSB/JKRSMRH/SEMALATONG/2024/022 | Concrete Mix Design (Supplier: Jak Hin) | 17/05/2024 | No objection |
| 8 | PTSB/JKRSMRH/SEMALATONG/2024/026 | Concrete Mix Design (Supplier: Hai Soon) | 21/05/2024 | No objection |
| 9 | PTSB/JKRSMRH/SEMALATONG/2024/040 | Proposed Spun Pile & RC Pile | 13/08/2024 | No objection |
| 10 | PTSB/JKRSMRH/SEMALATONG/2024/040 | Resubmission of Concrete Mix Design G50P (Supplier: Jak Hin) | 13/08/2024 | No objection |
| 11 | PTSB/JKRSMRH/SEMALATONG/2024/043 | Test Report for Fine Aggregate & Admixture | 15/08/2024 | No objection |
| 12 | PTSB/JKRSMRH/SEMALATONG/2024/054 | Borrow Pit Test Report - Bukit Lebor | 2/10/2024 | No objection |
| 13 | PTSB/JKRSMRH/SEMALATONG/2024/057 | Submission of Site Laboratory | 3/10/2024 | No objection |
| 14 | PTSB/JKRSMRH/SEMALATONG/2024/062 | Prestressed Concrete Girder | 24/10/2024 | No objection |
| 15 | PTSB/JKRSMRH/SEMALATONG/2024/066 | Mill Certificate and Company Profile for Reinforcement Bars | 11/11/2024 | No objection |
| 16 | PTSB/JKRSMRH/SEMALATONG/2024/080 | Submission of Mill Certificate T12 | 13/11/2024 | No objection |
| 17 | PTSB/JKRSMRH/SEMALATONG/2024/081 | Submission of Trial Mix Cube Test Strength Report - (Supplier : Jak Hin) | 13/11/2024 | No objection |
| 18 | PTSB/JKRSMRH/SEMALATONG/2024/082 | Asphaltic concrete supplier, Company profile & Mix Design for AC28 | 23/12/2024 | Resubmission through letter (2025/008) |
| 19 | PTSB/JKRSMRH/SEMALATONG/2024/087 | Rubber Bearing & Rubber Expansion Joint - Bridge | 15/01/2025 | No objection |
| 20 | PTSB/JKRSMRH/SEMALATONG/2025/008 | Asphaltic Concrete Mix Design (AC28 & AC14) | 27/02/2025 | No objection |
| 21 | PTSB/JKRSMRH/SEMALATONG/2025/023 | Official Test Report for 75mm DCR from Gunung Sibanyis & Site | 19/05/2025 | Resubmission through letter (2025/061) |
| 22 | PTSB/JKRSMRH/SEMALATONG/2025/037 | Compressions Stiffness & Shear Stiffness Test for Rubber Bearing | 7/07/2025 | No objection |
| 23 | PTSB/JKRSMRH/SEMALATONG/2025/046 | Submission of Mill Certificate T16 & Company Profile | 15/08/2025 | No objection |
| 24 | PTSB/JKRSMRH/SEMALATONG/2025/050 | Proposed Expobed(Fosroc) for Epoxy Mortar Plinth | 8/09/2025 | No objection |
| 25 | PTSB/JKRSMRH/SEMALATONG/2025/051 | Proposed Expobed(Fosroc) for Epoxy Mortar Plinth | 9/09/2025 | No objection |
| 26 | PTSB/JKRSMRH/SEMALATONG/2025/055 | Revised Concrete Mix Design G40N & G50P (Supplier : Jak Hin) | 17/09/2025 | No objection |
| 27 | PTSB/JKRSMRH/SEMALATONG/2025/061 | Official Test Report for 75mm DCR from Gunung Sibanyis | 2/10/2025 | No objection |
| 28 | PTSB/JKRSMRH/SEMALATONG/2025/063 | Proposed Cebex 100 Admixture for Non - Shrinkage Concrete Infill Pile Plug | 2/10/2025 | No objection |
| 29 | PTSB/JKRSMRH/SEMALATONG/2025/066 | Official Test Report for River Sand Sources from Sibu Sand | 7/10/2025 | No objection |
| 30 | PTSB/JKRSMRH/SEMALATONG/2025/070 | Proposed Curing Compound | 10/10/2025 | No objection |
| 31 | PTSB/JKRSMRH/SEMALATONG/2025/071 | Proposed Reinforcement Coupler -F-Tive Splicing Sdn. Bhd. | 12/10/2025 | No objection |
| 32 | PTSB/JKRSMRH/SEMALATONG/2025/077 | Proposed Borrow Pit - Simunjan | 11/11/2025 | No objection |
| 33 | PTSB/JKRSMRH/SEMALATONG/2025/078 | Submission of Concrete Mix Design Grade 40P Hai Shoon Concrete (Serian) | 11/11/2025 | No objection |
| 34 | PTSB/JKRSMRH/SEMALATONG/2025/083 | Proposed Subgrade Material (Sand) for CH 23+200 to CH 24+200 | 24/11/2025 | No objection |
| 35 | PTSB/JKRSMRH/SEMALATONG/2025/086 | Test Report for Tensile and Slip Test of Reinforcement Couplers | 25/11/2025 | No objection |
| 36 | PTSB/JKRSMRH/SEMALATONG/2025/087 | Tensile Test Report for Reinforcement Bar T16 & T10 | 8/12/2025 | No objection |
| 37 | PTSB/JKRSMRH/SEMALATONG/2025/090 | Proposed Borrow Pit - Semalatong Simunjan | 8/12/2025 | No objection |
| 38 | PTSB/JKRSMRH/SEMALATONG/2025/091 | Utilization of 75mm DCR as Replacement of Earth Material | 19/12/2025 | Resubmission through letter (2026/022) |
| 39 | PTSB/JKRSMRH/SEMALATONG/2025/092 | Proposed Borrow Pit at Semalatong | 30/12/2025 | No objection |
| 40 | PTSB/JKRSMRH/SEMALATONG/2026/011 | Concrete Mixed Design ICE Concrete | 9/03/2026 | No objection |
| 41 | PTSB/JKRSMRH/SEMALATONG/2026/014 | Revised Concrete Mixed Design Hai Shoon Concrete | 17/03/2026 | No objection |
| 42 | PTSB/JKRSMRH/SEMALATONG/2026/021 | RC Pile from Iprotech Company | 24/04/2026 | with comment, not approved |
| 43 | PTSB/JKRSMRH/SEMALATONG/2026/022 | Utilization of 75mm DCR as Replacement of Earth Material | 6/05/2026 | No objection |
| 44 | PTSB/JKRSMRH/SEMALATONG/2026/029 | Submission Of Tensile Test Report for T12 and T16 | 12/06/2026 | No objection |
| 45 | PTSB/JKRSMRH/SEMALATONG/2026/034 | Submission of Proposed Concrete Mix Design from Hailek Concrete | 23/07/2026 | No objection |
Method statement approval
CODE 1 Approved CODE 2 Commented, resubmit CODE 3 Not approved, resubmit
Major works must be at Code 1 before work proceeds on site.
Method statement register (29 items)
| No. | Reference No. | Description | Date Replied | Status / Remarks / Action |
|---|---|---|---|---|
| 1 | PTSB/JKRSMRH/SEMALATONG/2024/004 | Installation of Prefabricated Vertical Drain | 29/02/2024 | No objection, with comment |
| 2 | PTSB/JKRSMRH/SEMALATONG/2024/010 | Site Clearing Work | 7/03/2024 | No objection |
| 3 | Earthwork | |||
| 4 | Sandfill Work | |||
| 5 | Geotextile Laying Work | |||
| 6 | Subbase & Roadbase Laying | |||
| 7 | PTSB/JKRSMRH/SEMALATONG/2024/021 | MOS for Piling Works (250mmx250mm RCSQ Pile & 600mm Dia. Spun Pile) | 17/05/2024 | No objection |
| 8 | PTSB/JKRSMRH/SEMALATONG/2024/036 | Installation of HDPE Pipe Culvert | 6/08/2024 | No objection, with comment |
| 9 | PTSB/JKRSMRH/SEMALATONG/2024/044 | MOS for Dynamic Pile Load Test (PDA) | 16/08/2024 | No objection |
| 10 | PTSB/JKRSMRH/SEMALATONG/2024/048 | MOS for Maintained Load Test (MLT) | 29/08/2024 | Resubmission through letter (052) |
| 11 | PTSB/JKRSMRH/SEMALATONG/2024/052 | Resubmission of MLT (Spun Pile) | 12/09/2024 | Resubmission through letter (060) |
| 12 | PTSB/JKRSMRH/SEMALATONG/2024/052 | Endorsed Kentledge Setting Up Calculation (Spun Pile) | 12/09/2024 | Resubmission through letter (064) |
| 13 | PTSB/JKRSMRH/SEMALATONG/2024/060 | Resubmission of MLT (Spun Pile) | 14/10/2024 | Resubmission through letter (064) |
| 14 | PTSB/JKRSMRH/SEMALATONG/2024/063 | Proposed Replacement of Damaged Driven Test Pile (Spun Pile) | 24/10/2024 | No objection |
| 15 | PTSB/JKRSMRH/SEMALATONG/2024/064 | Resubmission Endorsed Kentledge Setting Out Calculation (Spun Pile) | 25/10/2024 | Resubmission through letter (077) |
| 16 | PTSB/JKRSMRH/SEMALATONG/2024/070 | Method Statement for MLT - Binareich Lab & Test S/B | 14/11/2024 | No objection |
| 17 | PTSB/JKRSMRH/SEMALATONG/2024/071 | MOS for High Strain Dynamic Pile Testing - Binareich | 15/11/2024 | No objection |
| 18 | PTSB/JKRSMRH/SEMALATONG/2024/076 | Method Statement for Pile Embankment Slab | 20/11/2024 | No objection |
| 19 | PTSB/JKRSMRH/SEMALATONG/2024/077 | Revised Piling Staging Analysis Report | 20/11/2024 | No objection |
| 20 | Letter of Undertaking for Temporary Piling Staging Design | 20/11/2024 | No objection | |
| 21 | PTSB/JKRSMRH/SEMALATONG/2025/006 | Method Statement for Topping up of Existing Road to Subbase Level | 26/02/2025 | Resubmission through letter (2025/040) |
| 22 | PTSB/JKRSMRH/SEMALATONG/2025/040 | Method Statement for Topping up of Existing Road to Subbase Level at CH9+000 - CH10+000 | 30/07/2025 | No objection, with comment |
| 23 | PTSB/JKRSMRH/SEMALATONG/2025/041 | Method Statement for the Casting of Post Tension Beams | 6/08/2025 | Resubmission through letter (2025/076) |
| 24 | PTSB/JKRSMRH/SEMALATONG/2025/059 | Method of Statement for Abutment Construction | 26/09/2025 | No objection |
| 25 | PTSB/JKRSMRH/SEMALATONG/2025/060 | MOS - Embankment Fill to Surcharge Level using DCR (CH5+400 - CH9+000) | 26/09/2025 | No objection, with comment |
| 26 | PTSB/JKRSMRH/SEMALATONG/2025/076 | MOS - Casting Post Tensioned Beams (Calculation Existing Piled Embankment) | 17/10/2025 | No objection |
| 27 | PTSB/JKRSMRH/SEMALATONG/2025/082 | Temporary Crossing at Sg. Spaoh | 24/11/2025 | No objection, with comment |
| 28 | PTSB/JKRSMRH/SEMALATONG/2025/090 | Method Statement for Rectification of Under Strength Concrete | 19/12/2025 | Resubmission through letter (2026/032) |
| 29 | PTSB/JKRSMRH/SEMALATONG/2026/032 | Submission Of Revised Method Statement for Under-Strength Concrete | 9/07/2026 | No objection |
All 6 NCRs closed
Settlement gauges not installed (CH1+700 – CH13+800)
Field density tests not carried out on embankment fill layers
G40N concrete below required 28-day strength
Pile protrusion and lean concrete not to drawing
Earth fill material not complying with gradation limits
Embankment filling (CH19+125 – CH19+425) without prior S.O. approval
NCR register (full text)
- Date issued
- 13/09/2024
- Received by
- Loh Cheng Yong
- Closed out
- TBA
The Contractor has not installed the rod settlement gauge between CH1+700 - CH13+800 (refer attachment 1.0). Installation of settlement gauge is compulsory as referred to Specifications of Particular Application [Part 3 (i)(b)]; Section 8; Sub-Section 6.2;"Settlement Gauges" & construction drawing no. PTSB/SMLT/ST/01 & 05 for detailed settlement monitoring purposes.
Due date: –
Proposal: The remaining settlement gauge will be installed continously for other required chainage.
- Date issued
- 13/09/2024
- Received by
- Loh Cheng Yong
- Closed out
- 10/11/2024
The Contractor has not conducted the soil Field Density Test for road embankment, between CH0+700 - CH2+000 & CH7+300 - CH7+500 respectively, for ongoing road embankment earth filling works (refer attachment 1.0). Soil Field Density Test shall be conducted for each compacted layer before proceeding the next stages of works, as referred to the Standard Specification For Road Works (JKR/SPJ/2013-S2); Section 2.2; Sub-Section 2.2.4.4;"Compaction".
Due date: –
Proposal: The pending FDT will be conducted concurrently for each 300mm layer of soil embankment.
- Date issued
- 20/01/2025
- Received by
- Loh Cheng Yong
- Closed out
- TBA
The contractor did not meet the required design strength (40 N/mm²) and target mean strength (47.38 N/mm²) for the G40N concrete grade in the 28-day cube compressive test. The average result was only 38.3 N/mm², with individual values of 34.7, 52.9, and 27.4 N/mm² for the 3 samples. (refer attachment 1.0 & 2.0)
Thus, the contractor must propose and submit a rectification works, endorsed by a Professional Engineer with Practicing Certificates, to the Superintending Officer for review and consideration before proceeding with the next stage of work.
The contractor is reminded to ensure that all concrete materials delivered to the site comply with the construction drawing, contract specifications (JKR/SPJ/2009-S9), and approved design mix.
Due date: –
Proposal: –
- Date issued
- 27/01/2025
- Received by
- Loh Cheng Yong
- Closed out
- 26/02/2025
The contractor failed to provide the protuded 75mm length (from the cut-off level to the top surface of the lean concrete) for the exposed RC pile head. Additionally, the constructed lean concrete was found to be damaged. (Refer attachment 1.0)
Thus, the contractor must propose and submit a rectification works, endorsed by a Professional Engineer with Practicing Certificates, to the Superintending Officer for review and consideration before proceeding with the next stage of work.
The contractor is reminded to ensure that all construction materials delivered to the site comply with the construction drawing and contract specifications (JKR/SPJ/2008-S9) accordingly.
Due date: –
Proposal: To remove & reconstruct the lean concrete as per construction drawing & contract specifications accordingly.
- Date issued
- 22/05/2025
- Received by
- Loh Cheng Yong
- Closed out
- 21/10/2025
Referring to your letter (GASB/JKR/GDSM/L138) & our letter (PTSB/JKRSMRH/SEMALATONG/2025/023), it was found out that the test results of the gradation limit is not comply with the specifications. Furthermore, these materials were delivered and placed on the existing plantation roads as part of the embankment fill for the proposed road alignment before the official test results were received as proposed by the contractor. (Refer to Site Memo No. 22)
This issue must be addressed as a priority. Please carry out all necessary corrective actions and ensure they are completed within 14 days from the date of this notice.
Kindly be reminded that the Method Statement and Material submission must be approved prior to proceeding with the next stage of the work.
Due date: –
Proposal: New samples has been taken for testing at approved accredited laboratory.
- Date issued
- 24/09/2025
- Received by
- Loh Cheng Yong
- Closed out
- TBA
It has come to our attention that earth filling works for the road embankment between CH19+425 and CH19+125 have been carried out without prior approval from Superintending Officer. (refer attachment 1.0)
Kindly take note of the following comments and observations:
1. Submission of locality plan and permit for the borrow pit is still pending.
2. Suitability test results for the borrow pit material have not yet been submitted.
3. Approval Chit for the backfilling activity is pending.
4. Drainage layer provided prior to backfilling is of insufficient width.
Please be reminded that it is the contractor's sole responsibility to ensure that all materials used and works executed are in full compliance with the approved contract specifications and construction drawings. Failure to comply with the above requirements shall be deemed as carrying out unauthorized works. The contractor will bear full responsibility for the consequences of such actions, including but not limited to any liabilities, defects, or claims that may arise.
Implementation of appropriate rectification measures shall be carried out without delay.
Due date: –
Proposal: –
Site memos
Works already behind schedule
Site Memo SM/PTSB/B084/042 · Delay Notification of Work Progress · issued 21/10/2026
Based on site progress as at 21/10/2026 against the Revised Work Programme Rev.01 (Ref.: L286), the following works have fallen behind schedule:
Piling works for Embankment B (scheduled to start 06/03/2026) and Abutment B (scheduled to start 15/09/2026) have yet to commence.
CRITICAL PATHSettlement gauge, free drainage layer, embankment fill and surcharge works have yet to commence. The surcharge period was scheduled to start 25/07/2026.
CRITICAL PATHPiling works for Embankment A (scheduled to start 22/05/2026) have yet to commence; slab concreting for Embankment B (scheduled to complete 25/04/2026) is only about 50% completed.
BEHIND SCHEDULELatest site memos
Laying of DCR over Surcharge Layer from Ch 0+000 to Ch 0+600
Notification of Compressive Strength of 31 days for Concrete Grade 40P
Earth Embankment Works
Notification of Compressive Strength of 11 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)
Notification of Compressive Strength of 10 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)
Delay Notification of Work Progress
Site memo register (42 memos)
| No. | Ref. No | Description | Date Issued | Status | Remarks |
|---|---|---|---|---|---|
| 1 | SM/PTSB/B084/001 | General Reminder - Installation of Road Settlement Gauge | 26/06/2024 | Close | |
| 2 | SM/PTSB/B084/002 | General Reminder - Submission of Soil Test Report for Bukit Lebor & Bukit Entengan Borrow Pit | 27/06/2024 | Close | |
| 3 | SM/PTSB/B084/003 | General Reminder - Installation of Traffic Signages | 27/06/2024 | Close | |
| 4 | SM/PTSB/B084/004 | General Reminder - Implementation of Field Density Testing | 4/07/2024 | Close | |
| 5 | SM/PTSB/B084/005 | General Reminder - Submission of Temporary Works (Staging System) at Sg. Simunjan Kanan River Bank. | 18/07/2024 | Close | |
| 6 | SM/PTSB/B084/006 | General Reminder - Provision of Site Office Facilities. | 18/07/2024 | Close | |
| 7 | SM/PTSB/B084/007 | General Reminder - Submission of Approval Chit Form (Period of July 2024). | 24/07/2024 | Close | |
| 8 | SM/PTSB/B084/008 | General Reminder - Reinstatement of Damage/Missing Rod Settlement Gauge. | 24/07/2024 | Close | |
| 9 | SM/PTSB/B084/009 | General Reminder - Sequence Of Work For Pipe Culvert Construction. | 30/07/2024 | Close | |
| 10 | SM/PTSB/B084/010 | Placement of Unrelated Construction Materials. | 6/09/2024 | Close | |
| 11 | SM/PTSB/B084/011 | Routine Testing for Geotextiles | 6/09/2024 | Close | |
| 12 | SM/PTSB/B084/012 | Damage of Geotextiles | 19/09/2024 | Close | |
| 13 | SM/PTSB/B084/013 | Piling Works (Test Pile) for 600mm Dia. Spun Pile | 3/10/2024 | Close | |
| 14 | SM/PTSB/B084/014 | Unset Piling Works (Test Pile) RC.SQ Pile 250mm | 3/10/2024 | Close | |
| 15 | SM/PTSB/B084/015 | Placement of Temporary Road Barrier | 7/10/2024 | Close | |
| 16 | SM/PTSB/B084/016 | Unset Piling Point - Sg. Simunjan Kanan Bridge Embankment A | 5/11/2024 | Close | |
| 17 | SM/PTSB/B084/017 | Notification of Compressive Strength of 7 days for Concrete Grade 40 | 31/12/2024 | Close | |
| 18 | SM/PTSB/B084/018 | Notification of Compressive Strength of 7 days for Concrete Grade 40 | 6/01/2025 | Close | |
| 19 | SM/PTSB/B084/019 | Insufficient of Road Formation Width | 15/01/2025 | Close | |
| 20 | SM/PTSB/B084/020 | Removal of Blockstone & Replacement With Suitable Materials | 14/02/2025 | Close | |
| 21 | SM/PTSB/B084/021 | Replacement of Soil Materials with DCR 3" for Road Embankment | 14/05/2025 | Close | |
| 22 | SM/PTSB/B084/022 | Slow Progress on Site | 15/05/2025 | Close | |
| 23 | SM/PTSB/B084/023 | Surcharge Works | 1/07/2025 | Close | |
| 24 | SM/PTSB/B084/024 | Insufficient Road Embankment Width (CH4+000 - CH5+700) | 21/07/2025 | Close | |
| 25 | SM/PTSB/B084/025 | Submission of Approval Chit Form (Period of July 2025) | 24/07/2025 | Close | |
| 26 | SM/PTSB/B084/026 | Fabrication of Bridge Girder Beam | 25/07/2025 | Close | |
| 27 | SM/PTSB/B084/027 | Settlement Monitoring Works | 11/08/2025 | Close | |
| 28 | SM/PTSB/B084/028 | Replacement of Soil Materials with DCR 3" for Road Embankment | 22/08/2025 | Close | |
| 29 | SM/PTSB/B084/029 | Notification of Compressive Strength of 28 days for Concrete Grade 40N | 20/10/2025 | Close | |
| 30 | SM/PTSB/B084/030 | Notification of Compressive Strength of 28 days for Concrete Grade 50P | 20/10/2025 | Close | |
| 31 | SM/PTSB/B084/031 | Temporary River Crossing at Sg. Spaoh | 30/10/2025 | Close | |
| 32 | SM/PTSB/B084/032 | Reminder on Mandatory Use of Personal Protective Equipment (PPE) On Site | 18/11/2025 | Close | |
| 33 | SM/PTSB/B084/033 | Damages Of Girder Beam No. 1 Type 40 (Flange) Sg. Simunjan Kanan Bridge | 5/12/2025 | Close | |
| 34 | SM/PTSB/B084/034 | Notification of Compressive Strength of 29 days for Concrete Grade 50P (Type16 Girder Beam No. 2, Sg. Simunjan Kanan Bridge) | 6/12/2025 | Close | |
| 35 | SM/PTSB/B084/035 | Notification of Compressive Strength of 7 days for Concrete Grade 40 (Pile Cap Pier 1 & Abutment Headwall Sg. Simunjan Kanan Bridge) | 10/12/2025 | Close | |
| 36 | SM/PTSB/B084/036 | Notification of Compressive Strength of 28 days for Concrete Grade 40P | 16/12/2025 | Close | |
| 37 | SM/PTSB/B084/037 | Laying of DCR over Surcharge Layer from Ch 0+000 to Ch 0+600 | 17/12/2025 | Close | |
| 38 | SM/PTSB/B084/038 | Notification of Compressive Strength of 31 days for Concrete Grade 40P | 20/02/2026 | Close | Hai Soon Concrete |
| 39 | SM/PTSB/B084/039 | Earth Embankment Works | 25/03/2026 | Close | |
| 40 | SM/PTSB/B084/040 | Notification of Compressive Strength of 11 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge) | 10/08/2026 | Close | Hai Soon Concrete |
| 41 | SM/PTSB/B084/041 | Notification of Compressive Strength of 10 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge) | 10/08/2026 | Close | Hai Soon Concrete |
| 42 | SM/PTSB/B084/042 | Delay Notification of Work Progress | 21/10/2026 | Open |
No RFIs or site queries this period
Site queries under review: nil for the reporting period 26-09-2026 to 25-10-2026.
1,783 tests passed to date
Tests per month
- 5 nos. of Field Density Test have been retested.
- Cumulative failed results cover: Field Density Test, cube test, PDA RCSQ pile (250 mm), PDA spun pile (600 mm dia.), rebound hammer test and aggregate test (DCR 3").
Tests by type (cumulative)
Test record by type
| No. | Description | Previous Month | Oct '26 | Total |
|---|---|---|---|---|
| 1 | Cube Test | 1,047 | 0 | 1,047 |
| 2 | Field Density Test (DCR) | 42 | 0 | 42 |
| 3 | Field Density (Soil) | 643 | 0 | 643 |
| 4 | Field Density Test (Existing) | 0 | 0 | 0 |
| 5 | Rebar Test | 7 | 0 | 7 |
| 6 | Premix Test | 0 | 0 | 0 |
| 7 | Borrow Pit Test | 8 | 0 | 8 |
| 8 | Pile Test for 250mm RCSQ Pile (PDA) | 29 | 0 | 29 |
| 9 | Pile Test 250mm RCSQ Pile (MLT) | 3 | 0 | 3 |
| 10 | Pile Test 600mm Dia. Spun Pile (PDA) | 26 | 0 | 26 |
| 11 | Pile Test 600mm Dia. Spun Pile (MLT) | 2 | 0 | 2 |
| 12 | Pile Integrity Testing (PIT) | 4 | 0 | 4 |
| 13 | Rebound Hammer Test | 9 | 0 | 9 |
| 14 | Dipping test (Subgrade) | 1 | 0 | 1 |
| 15 | Aggregate Test DCR 3" | 4 | 0 | 4 |
| Total | 1,825 | 0 | 1,825 |
Cube testing — pile embankment B, Sg. Spaoh
Field density testing — earth embankment fill
26 km Gedong – Semalatong: site progress video
Thank you
Questions & discussion
PTSB · QA/QC Monthly Report No. 33 · PWD/HO/B084/2023