REPORT NO.

33

AS OF

25 October 2026

QA/QC MONTHLY REPORT · NO. 33

Direct Negotiated Contract · Contract No. PWD/HO/B084/2023

Proposed Construction of Road
from Gedong to Kpg. Semalatong

Simunjan, Samarahan Division

Reporting period 26 Sep – 25 Oct 2026

Progress & QA/QC Meeting No. 33

CLIENT

Government of Sarawak

IMPLEMENTING AGENCY

Jabatan Kerja Raya Sarawak

CONSULTANT

Perunding Timur (S) Sdn Bhd

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

2

PROJECT PARTICULARS

Contract at a glance

Project title

Proposed Construction of Road from Gedong to Kampung Semalatong, Simunjan, Samarahan Division

Contract no.

PWD/HO/B084/2023

Client

Government of Sarawak

Superintending Officer

Jabatan Kerja Raya Samarahan

Consultant

Perunding Timur (S) Sdn. Bhd.

Contractor

Glumox Abiz Sdn. Bhd.

Insurance coverage

22/12/2023 to 21/06/2028

DOSH registration no.

TBA

Min. interim payment

RM 1,000.00

LAD

0.0182% of original contract sum

DLP

24 months

Contract sum

RM 233.53 M

RM 233,531,784.55

Original contract period

42 months

22/12/2023 – 21/06/2027

Revised completion date

28/01/2028

EOT 1, 2, 3 & 4: +221 days

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

3

PROJECT BRIEF

A shorter, direct link for Kpg. Semalatong

JKR Sarawak intends to take over and upgrade the existing plantation road from Gedong to Kpg. Semalatong, building a shorter, more direct and efficient link between the two.

The new road lets the people of Kpg. Semalatong reach Gedong, Simunjan and Serian towns to market their agricultural produce, and makes it easier to reach government offices.

About 20,017 villagers in the Gedong, Simunjan and Semalatong area will benefit.

20,017

villagers benefit — Gedong, Simunjan & Semalatong area

ROUTE (SCHEMATIC)

Kpg. Semalatong

Gedong

Simunjan · Serian
Pan Borneo Hwy

26 km R3 road

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

4

PROJECT OBJECTIVES

Why the road is being built

Shorter journeys

Shorten the travel distance from Kpg. Semalatong to the Pan Borneo Highway, Serian Town and Gedong.

Safe, reliable network

Provide a safe and reliable road network system.

Economic uplift

Ease transport of agricultural produce and logistics, raising the economic and social status of the area in support of the government's efforts to eliminate hardcore poverty.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

5

SCOPE OF WORKS

Project components

R3-standard premix road

26 km

Taking over the existing plantation road, Kpg. Gedong to Kpg. Semalatong

R.C. bridges

2 nos.

71.8 m span at Sg. Simunjan Kanan
29.4 m span at Sg. Spaoh

Topographical survey

Site investigation works

Site clearing & earthworks

Drainage works

Road furniture

Soil treatment of road foundation

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

6

CONTENTS

What this report covers

01

Background

Project organisation chart

Monthly quality meetings

Registered professionals & supervisors

02

Monthly QA/QC monitoring

At a glance

Approval chits

Material approval

Method statement approval

Non-conformance reports

Site memos

Requests for information

Testing record & site photos

Each item's summary is followed by its detailed register. Closing: site progress video.

01

Background

Organisation · Quality meetings · Registered personnel

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

8

1.1 ORGANISATION

Project consultant team (PTSB)

Ir. Liew Tze Khaw

Project Director

Chen Min Sang

Sr. Project Engineer

Felisia Kong

Project Designer

Christoper Nicol Ak James Mising

Resident Engineer

Denthiquecca Ringam

Asst. Resident Engineer

Kenneth Law Yik Lun

Inspector of Works

TBA

Inspector of Works

Direct negotiation basis · organisation chart updated as of 25 April 2025

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

9

1.2 QUALITY MEETINGS

32 progress & QA/QC meetings held

2024

No. 1

31 Jan

No. 2

4 Mar

No. 3

1 Apr

No. 4

30 Apr

No. 5

5 Jun

No. 6

10 Jul

No. 7

1 Aug

No. 8

3 Sep

No. 9

4 Oct

No. 10

6 Nov

No. 11

5 Dec

2025

No. 12

9 Jan

No. 13

6 Feb

No. 14

5 Mar

No. 15

16 Apr

No. 16

7 May

No. 17

10 Jun

No. 18

10 Jul

No. 19

6 Aug

No. 20

10 Sep

No. 21

9 Oct

No. 22

6 Nov

No. 23

4 Dec

2026

No. 24

14 Jan

No. 25

3 Feb

No. 26

26 Feb

No. 27

6 May

No. 28

6 May

No. 29

25 Jun

No. 30

3 Aug

No. 31

11 Sep

No. 32

5 Oct

Latest: Progress & QA/QC Meeting No. 32 — 5 October 2026

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

10

1.3 PERSONNEL

Registered professionals & accredited supervisors

Total certified personnel

11 / 11

available on site against certified requirement

RE TEAM

Professional (BEM)

5 / 5

available / certified

IOW (BEM)

1 / 1

available / certified

CONTRACTOR

Professional (BEM)

3 / 3

available / certified

QS (BQSM)

1 / 1

available / certified

Site Supervisor (CIDB)

0 / 0

available / certified

Professional: any personnel registered with the Board of Engineers Malaysia (BEM), i.e. Chief Resident Engineer, Resident Engineer, Assistant Resident Engineer, Project Manager or Site Engineer.

02

Monthly QA/QC monitoring

Reporting period 26 Sep – 25 Oct 2026

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

12

2.0 AT A GLANCE

QA/QC status as of 25 October 2026

Approval chits closed

87%

856 of 986 · 0 new this month

Materials at Code 1

45/45

0 under review · 0 new this month

Method statements at Code 1

29/29

0 under review · 0 new this month

Non-conformance reports

0 open

6 issued · 6 closed

Site memos issued

42

1 this period · 41 closed

Requests for information

0

None issued · none under review

Tests passed

1,783

43 failed · 5 retest · 1,831 total

THIS PERIOD

0 approval chits

1 site memos

0 tests

0 NCR · 0 RFI

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

13

2.1 APPROVAL CHITS

Approval chit requests

THIS MONTH (26 Sep – 25 Oct 2026)

0 submitted

0

approved

0

in progress

0%

closed

CUMULATIVE (to 25 October 2026)

986 submitted

852

approved

856

closed

87%

closed

Approval chits by work category (cumulative 986)Up to Sep '26Oct '260100200EARTHWORK / CLEARING / USM (283)Quality Testing (241)Ground treatment (240)Bridge Work (78)Concrete Work (69)Survey & Setting Out (48)Culvert Work (13)Drainage Work (10)Road Work (2)Road Furniture (2)

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

14

2.1 APPROVAL CHITS · DETAIL

Approval chit summary by work category

Description

Previous Month

Oct '26

Total

Remarks

EARTHWORK / CLEARING / USM

283

0

283

Drainage Work

10

0

10

Road Work

2

0

2

Culvert Work

13

0

13

Ground treatment

240

0

240

Survey & Setting Out

48

0

48

Bridge Work

78

0

78

Concrete Work

69

0

69

Quality Testing

241

0

241

Road Furniture

2

0

2

TOTAL

986

0

986

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

15

2.2 MATERIAL APPROVAL

Material approval

At Code 1 (approved)

45 / 45

cumulative materials received as of 25 October 2026

New submissions

0

Aug '26

0

Sep '26

0

Oct '26

Received (cumulative)

45

Omitted / cancelled: 0

Under review by RE team

0

awaiting decision

Code 2

0

commented, contractor to resubmit

Code 3

0

not approved, contractor to resubmit

CODE 1

Approved

CODE 2

Commented, resubmit

CODE 3

Not approved, resubmit

Major works must be at Code 1 before work proceeds on site. All Code 2 items are to be resubmitted for review and upgraded to Code 1.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

16

2.2 MATERIAL APPROVAL · DETAIL

Material approval register · items 1–16 (1 of 3)

No.

Reference No.

Description

Date Replied

Status / Remarks / Action

1

PTSB/JKRSMRH/SEMALATONG/2024/002

Proposed Non-Woven Geotextile Type 1 & 2

26/01/2024

No objection, with comment

2

PTSB/JKRSMRH/SEMALATONG/2024/004

Proposed Prefabricated Vertical Drain

29/02/2024

No objection

3

PTSB/JKRSMRH/SEMALATONG/2024/007

Proposed HDPE Pipe Culvert

4/03/2024

No objection, with comment

4

PTSB/JKRSMRH/SEMALATONG/2024/012

Test Report for 38mm & 75mm DCR Crushed Aggregate

12/03/2024

No objection

5

PTSB/JKRSMRH/SEMALATONG/2024/013

Test Report for Sand

2/04/2024

No objection, with comment

6

PTSB/JKRSMRH/SEMALATONG/2024/018

Proposed Precast 250mmx250mm RCSQ Pile

7/05/2024

No objection

7

PTSB/JKRSMRH/SEMALATONG/2024/022

Concrete Mix Design (Supplier: Jak Hin)

17/05/2024

No objection

8

PTSB/JKRSMRH/SEMALATONG/2024/026

Concrete Mix Design (Supplier: Hai Soon)

21/05/2024

No objection

9

PTSB/JKRSMRH/SEMALATONG/2024/040

Proposed Spun Pile & RC Pile

13/08/2024

No objection

10

PTSB/JKRSMRH/SEMALATONG/2024/040

Resubmission of Concrete Mix Design G50P (Supplier: Jak Hin)

13/08/2024

No objection

11

PTSB/JKRSMRH/SEMALATONG/2024/043

Test Report for Fine Aggregate & Admixture

15/08/2024

No objection

12

PTSB/JKRSMRH/SEMALATONG/2024/054

Borrow Pit Test Report - Bukit Lebor

2/10/2024

No objection

13

PTSB/JKRSMRH/SEMALATONG/2024/057

Submission of Site Laboratory

3/10/2024

No objection

14

PTSB/JKRSMRH/SEMALATONG/2024/062

Prestressed Concrete Girder

24/10/2024

No objection

15

PTSB/JKRSMRH/SEMALATONG/2024/066

Mill Certificate and Company Profile for Reinforcement Bars

11/11/2024

No objection

16

PTSB/JKRSMRH/SEMALATONG/2024/080

Submission of Mill Certificate T12

13/11/2024

No objection

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

17

2.2 MATERIAL APPROVAL · DETAIL

Material approval register · items 17–30 (2 of 3)

No.

Reference No.

Description

Date Replied

Status / Remarks / Action

17

PTSB/JKRSMRH/SEMALATONG/2024/081

Submission of Trial Mix Cube Test Strength Report - (Supplier : Jak Hin)

13/11/2024

No objection

18

PTSB/JKRSMRH/SEMALATONG/2024/082

Asphaltic concrete supplier, Company profile & Mix Design for AC28

23/12/2024

Resubmission through letter (2025/008)

19

PTSB/JKRSMRH/SEMALATONG/2024/087

Rubber Bearing & Rubber Expansion Joint - Bridge

15/01/2025

No objection

20

PTSB/JKRSMRH/SEMALATONG/2025/008

Asphaltic Concrete Mix Design (AC28 & AC14)

27/02/2025

No objection

21

PTSB/JKRSMRH/SEMALATONG/2025/023

Official Test Report for 75mm DCR from Gunung Sibanyis & Site

19/05/2025

Resubmission through letter (2025/061)

22

PTSB/JKRSMRH/SEMALATONG/2025/037

Compressions Stiffness & Shear Stiffness Test for Rubber Bearing

7/07/2025

No objection

23

PTSB/JKRSMRH/SEMALATONG/2025/046

Submission of Mill Certificate T16 & Company Profile

15/08/2025

No objection

24

PTSB/JKRSMRH/SEMALATONG/2025/050

Proposed Expobed(Fosroc) for Epoxy Mortar Plinth

8/09/2025

No objection

25

PTSB/JKRSMRH/SEMALATONG/2025/051

Proposed Expobed(Fosroc) for Epoxy Mortar Plinth

9/09/2025

No objection

26

PTSB/JKRSMRH/SEMALATONG/2025/055

Revised Concrete Mix Design G40N & G50P (Supplier : Jak Hin)

17/09/2025

No objection

27

PTSB/JKRSMRH/SEMALATONG/2025/061

Official Test Report for 75mm DCR from Gunung Sibanyis

2/10/2025

No objection

28

PTSB/JKRSMRH/SEMALATONG/2025/063

Proposed Cebex 100 Admixture for Non - Shrinkage Concrete Infill Pile Plug

2/10/2025

No objection

29

PTSB/JKRSMRH/SEMALATONG/2025/066

Official Test Report for River Sand Sources from Sibu Sand

7/10/2025

No objection

30

PTSB/JKRSMRH/SEMALATONG/2025/070

Proposed Curing Compound

10/10/2025

No objection

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

18

2.2 MATERIAL APPROVAL · DETAIL

Material approval register · items 31–45 (3 of 3)

No.

Reference No.

Description

Date Replied

Status / Remarks / Action

31

PTSB/JKRSMRH/SEMALATONG/2025/071

Proposed Reinforcement Coupler -F-Tive Splicing Sdn. Bhd.

12/10/2025

No objection

32

PTSB/JKRSMRH/SEMALATONG/2025/077

Proposed Borrow Pit - Simunjan

11/11/2025

No objection

33

PTSB/JKRSMRH/SEMALATONG/2025/078

Submission of Concrete Mix Design Grade 40P Hai Shoon Concrete (Serian)

11/11/2025

No objection

34

PTSB/JKRSMRH/SEMALATONG/2025/083

Proposed Subgrade Material (Sand) for CH 23+200 to CH 24+200

24/11/2025

No objection

35

PTSB/JKRSMRH/SEMALATONG/2025/086

Test Report for Tensile and Slip Test of Reinforcement Couplers

25/11/2025

No objection

36

PTSB/JKRSMRH/SEMALATONG/2025/087

Tensile Test Report for Reinforcement Bar T16 & T10

8/12/2025

No objection

37

PTSB/JKRSMRH/SEMALATONG/2025/090

Proposed Borrow Pit - Semalatong Simunjan

8/12/2025

No objection

38

PTSB/JKRSMRH/SEMALATONG/2025/091

Utilization of 75mm DCR as Replacement of Earth Material

19/12/2025

Resubmission through letter (2026/022)

39

PTSB/JKRSMRH/SEMALATONG/2025/092

Proposed Borrow Pit at Semalatong

30/12/2025

No objection

40

PTSB/JKRSMRH/SEMALATONG/2026/011

Concrete Mixed Design ICE Concrete

9/03/2026

No objection

41

PTSB/JKRSMRH/SEMALATONG/2026/014

Revised Concrete Mixed Design Hai Shoon Concrete

17/03/2026

No objection

42

PTSB/JKRSMRH/SEMALATONG/2026/021

RC Pile from Iprotech Company

24/04/2026

with comment, not approved

43

PTSB/JKRSMRH/SEMALATONG/2026/022

Utilization of 75mm DCR as Replacement of Earth Material

6/05/2026

No objection

44

PTSB/JKRSMRH/SEMALATONG/2026/029

Submission Of Tensile Test Report for T12 and T16

12/06/2026

No objection

45

PTSB/JKRSMRH/SEMALATONG/2026/034

Submission of Proposed Concrete Mix Design from Hailek Concrete

23/07/2026

No objection

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

19

2.3 METHOD STATEMENT

Method statement approval

At Code 1 (approved)

29 / 29

cumulative method statements received as of 25 October 2026

New submissions

0

Aug '26

0

Sep '26

0

Oct '26

Received (cumulative)

29

Omitted / cancelled: 0

Under review by RE team

0

awaiting decision

Code 2

0

commented, contractor to resubmit

Code 3

0

not approved, contractor to resubmit

CODE 1

Approved

CODE 2

Commented, resubmit

CODE 3

Not approved, resubmit

Major works must be at Code 1 before work proceeds on site. All Code 2 items are to be resubmitted for review and upgraded to Code 1.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

20

2.3 METHOD STATEMENT · DETAIL

Method statement register · items 1–11 (1 of 3)

No.

Reference No.

Description

Date Replied

Status / Remarks / Action

1

PTSB/JKRSMRH/SEMALATONG/2024/004

Installation of Prefabricated Vertical Drain

29/02/2024

No objection, with comment

2

PTSB/JKRSMRH/SEMALATONG/2024/010

Site Clearing Work

7/03/2024

No objection

3

Earthwork

4

Sandfill Work

5

Geotextile Laying Work

6

Subbase & Roadbase Laying

7

PTSB/JKRSMRH/SEMALATONG/2024/021

MOS for Piling Works (250mmx250mm RCSQ Pile & 600mm Dia. Spun Pile)

17/05/2024

No objection

8

PTSB/JKRSMRH/SEMALATONG/2024/036

Installation of HDPE Pipe Culvert

6/08/2024

No objection, with comment

9

PTSB/JKRSMRH/SEMALATONG/2024/044

MOS for Dynamic Pile Load Test (PDA)

16/08/2024

No objection

10

PTSB/JKRSMRH/SEMALATONG/2024/048

MOS for Maintained Load Test (MLT)

29/08/2024

Resubmission through letter (052)

11

PTSB/JKRSMRH/SEMALATONG/2024/052

Resubmission of MLT (Spun Pile)

12/09/2024

Resubmission through letter (060)

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

21

2.3 METHOD STATEMENT · DETAIL

Method statement register · items 12–21 (2 of 3)

No.

Reference No.

Description

Date Replied

Status / Remarks / Action

12

PTSB/JKRSMRH/SEMALATONG/2024/052

Endorsed Kentledge Setting Up Calculation (Spun Pile)

12/09/2024

Resubmission through letter (064)

13

PTSB/JKRSMRH/SEMALATONG/2024/060

Resubmission of MLT (Spun Pile)

14/10/2024

Resubmission through letter (064)

14

PTSB/JKRSMRH/SEMALATONG/2024/063

Proposed Replacement of Damaged Driven Test Pile (Spun Pile)

24/10/2024

No objection

15

PTSB/JKRSMRH/SEMALATONG/2024/064

Resubmission Endorsed Kentledge Setting Out Calculation (Spun Pile)

25/10/2024

Resubmission through letter (077)

16

PTSB/JKRSMRH/SEMALATONG/2024/070

Method Statement for MLT - Binareich Lab & Test S/B

14/11/2024

No objection

17

PTSB/JKRSMRH/SEMALATONG/2024/071

MOS for High Strain Dynamic Pile Testing - Binareich

15/11/2024

No objection

18

PTSB/JKRSMRH/SEMALATONG/2024/076

Method Statement for Pile Embankment Slab

20/11/2024

No objection

19

PTSB/JKRSMRH/SEMALATONG/2024/077

Revised Piling Staging Analysis Report

20/11/2024

No objection

20

Letter of Undertaking for Temporary Piling Staging Design

20/11/2024

No objection

21

PTSB/JKRSMRH/SEMALATONG/2025/006

Method Statement for Topping up of Existing Road to Subbase Level

26/02/2025

Resubmission through letter (2025/040)

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

22

2.3 METHOD STATEMENT · DETAIL

Method statement register · items 22–29 (3 of 3)

No.

Reference No.

Description

Date Replied

Status / Remarks / Action

22

PTSB/JKRSMRH/SEMALATONG/2025/040

Method Statement for Topping up of Existing Road to Subbase Level at CH9+000 - CH10+000

30/07/2025

No objection, with comment

23

PTSB/JKRSMRH/SEMALATONG/2025/041

Method Statement for the Casting of Post Tension Beams

6/08/2025

Resubmission through letter (2025/076)

24

PTSB/JKRSMRH/SEMALATONG/2025/059

Method of Statement for Abutment Construction

26/09/2025

No objection

25

PTSB/JKRSMRH/SEMALATONG/2025/060

MOS - Embankment Fill to Surcharge Level using DCR (CH5+400 - CH9+000)

26/09/2025

No objection, with comment

26

PTSB/JKRSMRH/SEMALATONG/2025/076

MOS - Casting Post Tensioned Beams (Calculation Existing Piled Embankment)

17/10/2025

No objection

27

PTSB/JKRSMRH/SEMALATONG/2025/082

Temporary Crossing at Sg. Spaoh

24/11/2025

No objection, with comment

28

PTSB/JKRSMRH/SEMALATONG/2025/090

Method Statement for Rectification of Under Strength Concrete

19/12/2025

Resubmission through letter (2026/032)

29

PTSB/JKRSMRH/SEMALATONG/2026/032

Submission Of Revised Method Statement for Under-Strength Concrete

9/07/2026

No objection

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

23

2.4 NON-CONFORMANCE

All 6 NCRs closed, none issued Aug – Oct

Open NCRs

0

Issued / closed (cumulative)

6 / 6

NCR issued

0

Aug '26

0

Sep '26

0

Oct '26

NCR 001

13 Sep 2024

Settlement gauges not installed (CH1+700 – CH13+800)

CLOSED

NCR 002

13 Sep 2024

Field density tests not carried out on embankment fill layers

CLOSED

NCR 003

20 Jan 2025

G40N concrete below required 28-day strength

CLOSED

NCR 004

27 Jan 2025

Pile protrusion and lean concrete not to drawing

CLOSED

NCR 005

22 May 2025

Earth fill material not complying with gradation limits

CLOSED

NCR 006

24 Sep 2025

Embankment filling (CH19+125 – CH19+425) without prior S.O. approval

CLOSED

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

24

2.4 NON-CONFORMANCE · DETAIL

NCR register · NCR 001, NCR 002 (1 of 5)

No.

Ref. No

Description

Date Issued

Received By

Closed Out Date

Status

Remarks

1

NCR/PTSB/B084/001

The Contractor has not installed the rod settlement gauge between CH1+700 - CH13+800 (refer attachment 1.0). Installation of settlement gauge is compulsory as referred to Specifications of Particular Application [Part 3 (i)(b)]; Section 8; Sub-Section 6.2;"Settlement Gauges" & construction drawing no. PTSB/SMLT/ST/01 & 05 for detailed settlement monitoring purposes.

13/09/2024

Loh Cheng Yong

TBA

Close

Corrective Action By Contractor

Due Date

Proposal

The remaining settlement gauge will be installed continously for other required chainage.

2

NCR/PTSB/B084/002

The Contractor has not conducted the soil Field Density Test for road embankment, between CH0+700 - CH2+000 & CH7+300 - CH7+500 respectively, for ongoing road embankment earth filling works (refer attachment 1.0). Soil Field Density Test shall be conducted for each compacted layer before proceeding the next stages of works, as referred to the Standard Specification For Road Works (JKR/SPJ/2013-S2); Section 2.2; Sub-Section 2.2.4.4;"Compaction".

13/09/2024

Loh Cheng Yong

10/11/2024

Close

Corrective Action By Contractor

Due Date

Proposal

The pending FDT will be conducted concurrently for each 300mm layer of soil embankment.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

25

2.4 NON-CONFORMANCE · DETAIL

NCR register · NCR 003 (2 of 5)

No.

Ref. No

Description

Date Issued

Received By

Closed Out Date

Status

Remarks

3

NCR/PTSB/B084/003

The contractor did not meet the required design strength (40 N/mm²) and target mean strength (47.38 N/mm²) for the G40N concrete grade in the 28-day cube compressive test. The average result was only 38.3 N/mm², with individual values of 34.7, 52.9, and 27.4 N/mm² for the 3 samples. (refer attachment 1.0 & 2.0)

Thus, the contractor must propose and submit a rectification works, endorsed by a Professional Engineer with Practicing Certificates, to the Superintending Officer for review and consideration before proceeding with the next stage of work.

The contractor is reminded to ensure that all concrete materials delivered to the site comply with the construction drawing, contract specifications (JKR/SPJ/2009-S9), and approved design mix.

20/01/2025

Loh Cheng Yong

TBA

Close

Corrective Action By Contractor

Due Date

Proposal

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

26

2.4 NON-CONFORMANCE · DETAIL

NCR register · NCR 004 (3 of 5)

No.

Ref. No

Description

Date Issued

Received By

Closed Out Date

Status

Remarks

4

NCR/PTSB/B084/004

The contractor failed to provide the protuded 75mm length (from the cut-off level to the top surface of the lean concrete) for the exposed RC pile head. Additionally, the constructed lean concrete was found to be damaged. (Refer attachment 1.0)

Thus, the contractor must propose and submit a rectification works, endorsed by a Professional Engineer with Practicing Certificates, to the Superintending Officer for review and consideration before proceeding with the next stage of work.

The contractor is reminded to ensure that all construction materials delivered to the site comply with the construction drawing and contract specifications (JKR/SPJ/2008-S9) accordingly.

27/01/2025

Loh Cheng Yong

26/02/2025

Close

Corrective Action By Contractor

Due Date

Proposal

To remove & reconstruct the lean concrete as per construction drawing & contract specifications accordingly.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

27

2.4 NON-CONFORMANCE · DETAIL

NCR register · NCR 005 (4 of 5)

No.

Ref. No

Description

Date Issued

Received By

Closed Out Date

Status

Remarks

5

NCR/PTSB/B084/005

Referring to your letter (GASB/JKR/GDSM/L138) & our letter (PTSB/JKRSMRH/SEMALATONG/2025/023), it was found out that the test results of the gradation limit is not comply with the specifications. Furthermore, these materials were delivered and placed on the existing plantation roads as part of the embankment fill for the proposed road alignment before the official test results were received as proposed by the contractor. (Refer to Site Memo No. 22)

This issue must be addressed as a priority. Please carry out all necessary corrective actions and ensure they are completed within 14 days from the date of this notice.

Kindly be reminded that the Method Statement and Material submission must be approved prior to proceeding with the next stage of the work.

22/05/2025

Loh Cheng Yong

21/10/2025

Close

Corrective Action By Contractor

Due Date

Proposal

New samples has been taken for testing at approved accredited laboratory.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

28

2.4 NON-CONFORMANCE · DETAIL

NCR register · NCR 006 (5 of 5)

No.

Ref. No

Description

Date Issued

Received By

Closed Out Date

Status

Remarks

6

NCR/PTSB/B084/006

It has come to our attention that earth filling works for the road embankment between CH19+425 and CH19+125 have been carried out without prior approval from Superintending Officer. (refer attachment 1.0)

Kindly take note of the following comments and observations:

1. Submission of locality plan and permit for the borrow pit is still pending.

2. Suitability test results for the borrow pit material have not yet been submitted.

3. Approval Chit for the backfilling activity is pending.

4. Drainage layer provided prior to backfilling is of insufficient width.

Please be reminded that it is the contractor's sole responsibility to ensure that all materials used and works executed are in full compliance with the approved contract specifications and construction drawings. Failure to comply with the above requirements shall be deemed as carrying out unauthorized works. The contractor will bear full responsibility for the consequences of such actions, including but not limited to any liabilities, defects, or claims that may arise.

Implementation of appropriate rectification measures shall be carried out without delay.

24/09/2025

Loh Cheng Yong

TBA

Close

Corrective Action By Contractor

Due Date

Proposal

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

29

2.5 SITE MEMOS

Site memos

Issued (cumulative)

42

Open / closed

1 / 41

Site memos issued

0

Aug '26

2

Sep '26

1

Oct '26

LATEST SITE MEMOS

Ref.

Subject

Date issued

SM/037

Laying of DCR over Surcharge Layer from Ch 0+000 to Ch 0+600

17/12/2025

SM/038

Notification of Compressive Strength of 31 days for Concrete Grade 40P

20/02/2026

SM/039

Earth Embankment Works

25/03/2026

SM/040

Notification of Compressive Strength of 11 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)

10/08/2026

SM/041

Notification of Compressive Strength of 10 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)

10/08/2026

SM/042

Delay Notification of Work Progress

21/10/2026

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

30

2.5 SITE MEMOS · ISSUED THIS PERIOD

Works already behind schedule

Site Memo SM/PTSB/B084/042 · Delay Notification of Work Progress · issued 21/10/2026

Based on site progress as at 21/10/2026 against the Revised Work Programme Rev.01 (Ref.: L286), the following works have fallen behind schedule:

a

Sg. Simunjan Kanan Bridge

Piling works for Embankment B (scheduled to start 06/03/2026) and Abutment B (scheduled to start 15/09/2026) have yet to commence.

CRITICAL PATH

b

Earthworks Ch 14+876 – Ch 18+400

Settlement gauge, free drainage layer, embankment fill and surcharge works have yet to commence. The surcharge period was scheduled to start 25/07/2026.

CRITICAL PATH

c

Sg. Spaoh Bridge

Piling works for Embankment A (scheduled to start 22/05/2026) have yet to commence; slab concreting for Embankment B (scheduled to complete 25/04/2026) is only about 50% completed.

BEHIND SCHEDULE

KEY POINT Items (a) and (b) are on the critical path and, if not recovered, will affect the completion of the Works.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

31

2.5 SITE MEMOS · DETAIL

Site memo register · SM 001 – 014 (1 of 3)

No.

Ref. No

Description

Date Issued

Status

Remarks

1

SM/PTSB/B084/001

General Reminder - Installation of Road Settlement Gauge

26/06/2024

Close

2

SM/PTSB/B084/002

General Reminder - Submission of Soil Test Report for Bukit Lebor & Bukit Entengan Borrow Pit

27/06/2024

Close

3

SM/PTSB/B084/003

General Reminder - Installation of Traffic Signages

27/06/2024

Close

4

SM/PTSB/B084/004

General Reminder - Implementation of Field Density Testing

4/07/2024

Close

5

SM/PTSB/B084/005

General Reminder - Submission of Temporary Works (Staging System) at Sg. Simunjan Kanan River Bank.

18/07/2024

Close

6

SM/PTSB/B084/006

General Reminder - Provision of Site Office Facilities.

18/07/2024

Close

7

SM/PTSB/B084/007

General Reminder - Submission of Approval Chit Form (Period of July 2024).

24/07/2024

Close

8

SM/PTSB/B084/008

General Reminder - Reinstatement of Damage/Missing Rod Settlement Gauge.

24/07/2024

Close

9

SM/PTSB/B084/009

General Reminder - Sequence Of Work For Pipe Culvert Construction.

30/07/2024

Close

10

SM/PTSB/B084/010

Placement of Unrelated Construction Materials.

6/09/2024

Close

11

SM/PTSB/B084/011

Routine Testing for Geotextiles

6/09/2024

Close

12

SM/PTSB/B084/012

Damage of Geotextiles

19/09/2024

Close

13

SM/PTSB/B084/013

Piling Works (Test Pile) for 600mm Dia. Spun Pile

3/10/2024

Close

14

SM/PTSB/B084/014

Unset Piling Works (Test Pile) RC.SQ Pile 250mm

3/10/2024

Close

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

32

2.5 SITE MEMOS · DETAIL

Site memo register · SM 015 – 029 (2 of 3)

No.

Ref. No

Description

Date Issued

Status

Remarks

15

SM/PTSB/B084/015

Placement of Temporary Road Barrier

7/10/2024

Close

16

SM/PTSB/B084/016

Unset Piling Point - Sg. Simunjan Kanan Bridge Embankment A

5/11/2024

Close

17

SM/PTSB/B084/017

Notification of Compressive Strength of 7 days for Concrete Grade 40

31/12/2024

Close

18

SM/PTSB/B084/018

Notification of Compressive Strength of 7 days for Concrete Grade 40

6/01/2025

Close

19

SM/PTSB/B084/019

Insufficient of Road Formation Width

15/01/2025

Close

20

SM/PTSB/B084/020

Removal of Blockstone & Replacement With Suitable Materials

14/02/2025

Close

21

SM/PTSB/B084/021

Replacement of Soil Materials with DCR 3" for Road Embankment

14/05/2025

Close

22

SM/PTSB/B084/022

Slow Progress on Site

15/05/2025

Close

23

SM/PTSB/B084/023

Surcharge Works

1/07/2025

Close

24

SM/PTSB/B084/024

Insufficient Road Embankment Width (CH4+000 - CH5+700)

21/07/2025

Close

25

SM/PTSB/B084/025

Submission of Approval Chit Form (Period of July 2025)

24/07/2025

Close

26

SM/PTSB/B084/026

Fabrication of Bridge Girder Beam

25/07/2025

Close

27

SM/PTSB/B084/027

Settlement Monitoring Works

11/08/2025

Close

28

SM/PTSB/B084/028

Replacement of Soil Materials with DCR 3" for Road Embankment

22/08/2025

Close

29

SM/PTSB/B084/029

Notification of Compressive Strength of 28 days for Concrete Grade 40N

20/10/2025

Close

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

33

2.5 SITE MEMOS · DETAIL

Site memo register · SM 030 – 042 (3 of 3)

No.

Ref. No

Description

Date Issued

Status

Remarks

30

SM/PTSB/B084/030

Notification of Compressive Strength of 28 days for Concrete Grade 50P

20/10/2025

Close

31

SM/PTSB/B084/031

Temporary River Crossing at Sg. Spaoh

30/10/2025

Close

32

SM/PTSB/B084/032

Reminder on Mandatory Use of Personal Protective Equipment (PPE) On Site

18/11/2025

Close

33

SM/PTSB/B084/033

Damages Of Girder Beam No. 1 Type 40 (Flange) Sg. Simunjan Kanan Bridge

5/12/2025

Close

34

SM/PTSB/B084/034

Notification of Compressive Strength of 29 days for Concrete Grade 50P (Type16 Girder Beam No. 2, Sg. Simunjan Kanan Bridge)

6/12/2025

Close

35

SM/PTSB/B084/035

Notification of Compressive Strength of 7 days for Concrete Grade 40 (Pile Cap Pier 1 & Abutment Headwall Sg. Simunjan Kanan Bridge)

10/12/2025

Close

36

SM/PTSB/B084/036

Notification of Compressive Strength of 28 days for Concrete Grade 40P

16/12/2025

Close

37

SM/PTSB/B084/037

Laying of DCR over Surcharge Layer from Ch 0+000 to Ch 0+600

17/12/2025

Close

38

SM/PTSB/B084/038

Notification of Compressive Strength of 31 days for Concrete Grade 40P

20/02/2026

Close

Hai Soon Concrete

39

SM/PTSB/B084/039

Earth Embankment Works

25/03/2026

Close

40

SM/PTSB/B084/040

Notification of Compressive Strength of 11 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)

10/08/2026

Close

Hai Soon Concrete

41

SM/PTSB/B084/041

Notification of Compressive Strength of 10 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)

10/08/2026

Close

Hai Soon Concrete

42

SM/PTSB/B084/042

Delay Notification of Work Progress

21/10/2026

Open

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

34

2.6 REQUESTS FOR INFORMATION

No RFIs or site queries this period

Issued (cumulative)

0

Under review (cumulative)

0

Closed (cumulative)

0

RFI issued

0

Aug '26

0

Sep '26

0

Oct '26

Site queries under review

Nil for the reporting period 26-09-2026 to 25-10-2026.

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

35

2.7 TESTING

1,783 tests passed to date

Passed (cumulative)

1,783

Failed (cumulative)

43

Retest (cumulative)

5

Total (cumulative)

1,831

Tests carried out per monthAug '26103Sep '2676Oct '260

Remarks

5 nos. of Field Density Test have been retested.

Cumulative failed results cover: Field Density Test, cube test, PDA RCSQ pile (250 mm), PDA spun pile (600 mm dia.), rebound hammer test and aggregate test (DCR 3").

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

36

2.7 TESTING

Tests by type (cumulative)

Cube Test

1,047

+0 this month

Field Density (Soil)

643

+0 this month

THIS MONTH 0 tests

Other testsField Density Test (DCR)42Pile Test for 250mm RCSQ Pile (PDA)29Pile Test 600mm Dia. Spun Pile (PDA)26Rebound Hammer Test9Borrow Pit Test8Rebar Test7Pile Integrity Testing (PIT)4Aggregate Test DCR 3"4Pile Test 250mm RCSQ Pile (MLT)3Pile Test 600mm Dia. Spun Pile (MLT)2Dipping test (Subgrade)1

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

37

2.7 TESTING · DETAIL

Test record by type

No.

Description

Previous Month

Oct '26

Total

Remarks

1

Cube Test

1,047

0

1,047

2

Field Density Test (DCR)

42

0

42

3

Field Density (Soil)

643

0

643

4

Field Density Test (Existing)

0

0

0

5

Rebar Test

7

0

7

6

Premix Test

0

0

0

7

Borrow Pit Test

8

0

8

8

Pile Test for 250mm RCSQ Pile (PDA)

29

0

29

9

Pile Test 250mm RCSQ Pile (MLT)

3

0

3

10

Pile Test 600mm Dia. Spun Pile (PDA)

26

0

26

11

Pile Test 600mm Dia. Spun Pile (MLT)

2

0

2

12

Pile Integrity Testing (PIT)

4

0

4

13

Rebound Hammer Test

9

0

9

14

Dipping test (Subgrade)

1

0

1

15

Aggregate Test DCR 3"

4

0

4

Total

1,825

0

1,825

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

38

2.7 TESTING · SITE RECORD

Cube testing — pile embankment B, Sg. Spaoh

Photo 1 · 29-day cube test, pile embankment B @ Sg. Spaoh (G/L A–H / 11–15)

Photo 2 · 29-day cube test result, pile embankment B @ Sg. Spaoh

PTSB · QA/QC Monthly Report No. 33 · Gedong – Kpg. Semalatong Road (PWD/HO/B084/2023)

39

2.7 TESTING · SITE RECORD

Field density testing — earth embankment fill

Photo 3 · Field density test, earth embankment fill @ CH21+925

Photo 4 · Field density test, earth embankment fill @ CH23+175

SITE PROGRESS

26 km Gedong – Semalatong: site progress video

Video to be inserted

Thank you

Questions & discussion

IMPLEMENTING AGENCY

Jabatan Kerja Raya Sarawak

Wisma Saberkas, Jalan Tun Abang Haji Openg
93582 Kuching, Sarawak, Malaysia

CONSULTANT

Perunding Timur (S) Sdn Bhd

4th & 5th Floor "Stallion", Sublot 17, Rock Commercial Centre
1½ Mile, Jalan Rock, 93200 Kuching, Sarawak

CLIENT

Government of Sarawak

IMPLEMENTING AGENCY

Jabatan Kerja Raya Sarawak

CONSULTANT

Perunding Timur (S) Sdn Bhd

QA/QC MONTHLY REPORT · NO. 33
REPORT NO.33AS OF25 October 2026

Proposed Construction of Road from Gedong to Kpg. Semalatong

Simunjan, Samarahan Division
Direct Negotiated Contract · PWD/HO/B084/2023

Reporting period 26 Sep – 25 Oct 2026
Progress & QA/QC Meeting No. 33

ClientGovernment of Sarawak
Implementing agencyJabatan Kerja Raya Sarawak
ConsultantPerunding Timur (S) Sdn Bhd
PROJECT PARTICULARS

Contract at a glance

Contract sum
RM 233.53 M
RM 233,531,784.55
Contract period
42 months
22/12/2023 – 21/06/2027
Revised completion date
28/01/2028
EOT 1, 2, 3 & 4: +221 days
Project title
Proposed Construction of Road from Gedong to Kampung Semalatong, Simunjan, Samarahan Division
Contract no.
PWD/HO/B084/2023
Client
Government of Sarawak
Superintending Officer
Jabatan Kerja Raya Samarahan
Consultant
Perunding Timur (S) Sdn. Bhd.
Contractor
Glumox Abiz Sdn. Bhd.
Insurance coverage
22/12/2023 to 21/06/2028
DOSH registration no.
TBA
Min. interim payment
RM 1,000.00
LAD
0.0182% of original contract sum
DLP
24 months
PROJECT BRIEF

A shorter, direct link for Kpg. Semalatong

JKR Sarawak intends to take over and upgrade the existing plantation road from Gedong to Kpg. Semalatong, building a shorter, more direct and efficient link between the two.

The new road lets the people of Kpg. Semalatong reach Gedong, Simunjan and Serian towns to market their agricultural produce, and makes it easier to reach government offices.

Villagers who benefit
20,017
Gedong, Simunjan & Semalatong area

Objectives

Shorter journeys

Shorten the travel distance from Kpg. Semalatong to the Pan Borneo Highway, Serian Town and Gedong.

Safe, reliable network

Provide a safe and reliable road network system.

Economic uplift

Ease transport of agricultural produce and logistics, raising the economic and social status of the area in support of the government's efforts to eliminate hardcore poverty.

SCOPE OF WORKS

Project components

R3-standard premix road
26 km
Kpg. Gedong to Kpg. Semalatong
R.C. bridges
2 nos.
71.8 m Sg. Simunjan Kanan · 29.4 m Sg. Spaoh
Topographical survey
Site investigation works
Site clearing & earthworks
Drainage works
Road furniture
Soil treatment of road foundation
01 · BACKGROUND

Organisation, meetings & personnel

Project consultant team (PTSB)

Ir. Liew Tze Khaw

Project Director

Chen Min SangSr. Project Engineer
Felisia KongProject Designer
Christoper Nicol Ak James MisingResident Engineer
Denthiquecca RingamAsst. Resident Engineer
Kenneth Law Yik LunInspector of Works
TBAInspector of Works

Organisation chart updated as of 25 April 2025.

32 progress & QA/QC meetings held

2024
No. 131 JanNo. 24 MarNo. 31 AprNo. 430 AprNo. 55 JunNo. 610 JulNo. 71 AugNo. 83 SepNo. 94 OctNo. 106 NovNo. 115 Dec
2025
No. 129 JanNo. 136 FebNo. 145 MarNo. 1516 AprNo. 167 MayNo. 1710 JunNo. 1810 JulNo. 196 AugNo. 2010 SepNo. 219 OctNo. 226 NovNo. 234 Dec
2026
No. 2414 JanNo. 253 FebNo. 2626 FebNo. 276 MayNo. 286 MayNo. 2925 JunNo. 303 AugNo. 3111 SepNo. 325 Oct

Registered professionals & supervisors

Total certified personnel
11 / 11
available / certified
RE TEAM
Professional (BEM)
5 / 5
available / certified
IOW (BEM)
1 / 1
available / certified
CONTRACTOR
Professional (BEM)
3 / 3
available / certified
QS (BQSM)
1 / 1
available / certified
Site Supervisor (CIDB)
0 / 0
available / certified

Professional: any personnel registered with the Board of Engineers Malaysia (BEM), i.e. Chief Resident Engineer, Resident Engineer, Assistant Resident Engineer, Project Manager or Site Engineer.

02 · MONTHLY QA/QC

QA/QC status as of 25 October 2026

Reporting period 26 Sep – 25 Oct 2026

Approval chits closed
87%
856 of 986
Materials at Code 1
45/45
0 under review
Method statements at Code 1
29/29
0 under review
NCRs
0 open
6 issued · 6 closed
Site memos issued
42
1 open · 41 closed
RFIs
0
0 under review
Tests passed
1,783
43 failed · 5 retest
THIS PERIOD
0 approval chits
1 site memos
0 tests
0 NCR · 0 RFI
2.1 APPROVAL CHITS

Approval chit requests

THIS MONTH (26 Sep – 25 Oct 2026)
Submitted
0
Approved
0
Closed
0%
CUMULATIVE (to 25 October 2026)
Submitted
986
Approved
852
Closed
87%

By work category (cumulative 986)

EARTHWORK / CLEARING / USM
283
Quality Testing
241
Ground treatment
240
Bridge Work
78
Concrete Work
69
Survey & Setting Out
48
Culvert Work
13
Drainage Work
10
Road Work
2
Road Furniture
2
Up to Sep '26Oct '26
Approval chit summary table
Swipe the table sideways to see all columns.
DescriptionPrevious MonthOct '26Total
EARTHWORK / CLEARING / USM2830283
Drainage Work10010
Road Work202
Culvert Work13013
Ground treatment2400240
Survey & Setting Out48048
Bridge Work78078
Concrete Work69069
Quality Testing2410241
Road Furniture202
TOTAL9860986
2.2 MATERIAL APPROVAL

Material approval

At Code 1 (approved)
45 / 45
cumulative, as of 25 October 2026
New submissions
0Aug '26
0Sep '26
0Oct '26
Under review
0
Code 2 · resubmit
0
Code 3 · not approved
0
Omitted / cancelled
0

CODE 1 Approved CODE 2 Commented, resubmit CODE 3 Not approved, resubmit
Major works must be at Code 1 before work proceeds on site.

Material approval register (45 items)
Swipe the table sideways to see all columns.
No.Reference No.DescriptionDate RepliedStatus / Remarks / Action
1PTSB/JKRSMRH/SEMALATONG/2024/002Proposed Non-Woven Geotextile Type 1 & 226/01/2024No objection, with comment
2PTSB/JKRSMRH/SEMALATONG/2024/004Proposed Prefabricated Vertical Drain29/02/2024No objection
3PTSB/JKRSMRH/SEMALATONG/2024/007Proposed HDPE Pipe Culvert4/03/2024No objection, with comment
4PTSB/JKRSMRH/SEMALATONG/2024/012Test Report for 38mm & 75mm DCR Crushed Aggregate12/03/2024No objection
5PTSB/JKRSMRH/SEMALATONG/2024/013Test Report for Sand2/04/2024No objection, with comment
6PTSB/JKRSMRH/SEMALATONG/2024/018Proposed Precast 250mmx250mm RCSQ Pile7/05/2024No objection
7PTSB/JKRSMRH/SEMALATONG/2024/022Concrete Mix Design (Supplier: Jak Hin)17/05/2024No objection
8PTSB/JKRSMRH/SEMALATONG/2024/026Concrete Mix Design (Supplier: Hai Soon)21/05/2024No objection
9PTSB/JKRSMRH/SEMALATONG/2024/040Proposed Spun Pile & RC Pile13/08/2024No objection
10PTSB/JKRSMRH/SEMALATONG/2024/040Resubmission of Concrete Mix Design G50P (Supplier: Jak Hin)13/08/2024No objection
11PTSB/JKRSMRH/SEMALATONG/2024/043Test Report for Fine Aggregate & Admixture15/08/2024No objection
12PTSB/JKRSMRH/SEMALATONG/2024/054Borrow Pit Test Report - Bukit Lebor2/10/2024No objection
13PTSB/JKRSMRH/SEMALATONG/2024/057Submission of Site Laboratory3/10/2024No objection
14PTSB/JKRSMRH/SEMALATONG/2024/062Prestressed Concrete Girder24/10/2024No objection
15PTSB/JKRSMRH/SEMALATONG/2024/066Mill Certificate and Company Profile for Reinforcement Bars11/11/2024No objection
16PTSB/JKRSMRH/SEMALATONG/2024/080Submission of Mill Certificate T1213/11/2024No objection
17PTSB/JKRSMRH/SEMALATONG/2024/081Submission of Trial Mix Cube Test Strength Report - (Supplier : Jak Hin)13/11/2024No objection
18PTSB/JKRSMRH/SEMALATONG/2024/082Asphaltic concrete supplier, Company profile & Mix Design for AC2823/12/2024Resubmission through letter (2025/008)
19PTSB/JKRSMRH/SEMALATONG/2024/087Rubber Bearing & Rubber Expansion Joint - Bridge15/01/2025No objection
20PTSB/JKRSMRH/SEMALATONG/2025/008Asphaltic Concrete Mix Design (AC28 & AC14)27/02/2025No objection
21PTSB/JKRSMRH/SEMALATONG/2025/023Official Test Report for 75mm DCR from Gunung Sibanyis & Site19/05/2025Resubmission through letter (2025/061)
22PTSB/JKRSMRH/SEMALATONG/2025/037Compressions Stiffness & Shear Stiffness Test for Rubber Bearing7/07/2025No objection
23PTSB/JKRSMRH/SEMALATONG/2025/046Submission of Mill Certificate T16 & Company Profile15/08/2025No objection
24PTSB/JKRSMRH/SEMALATONG/2025/050Proposed Expobed(Fosroc) for Epoxy Mortar Plinth8/09/2025No objection
25PTSB/JKRSMRH/SEMALATONG/2025/051Proposed Expobed(Fosroc) for Epoxy Mortar Plinth9/09/2025No objection
26PTSB/JKRSMRH/SEMALATONG/2025/055Revised Concrete Mix Design G40N & G50P (Supplier : Jak Hin)17/09/2025No objection
27PTSB/JKRSMRH/SEMALATONG/2025/061Official Test Report for 75mm DCR from Gunung Sibanyis2/10/2025No objection
28PTSB/JKRSMRH/SEMALATONG/2025/063Proposed Cebex 100 Admixture for Non - Shrinkage Concrete Infill Pile Plug2/10/2025No objection
29PTSB/JKRSMRH/SEMALATONG/2025/066Official Test Report for River Sand Sources from Sibu Sand7/10/2025No objection
30PTSB/JKRSMRH/SEMALATONG/2025/070Proposed Curing Compound10/10/2025No objection
31PTSB/JKRSMRH/SEMALATONG/2025/071Proposed Reinforcement Coupler -F-Tive Splicing Sdn. Bhd.12/10/2025No objection
32PTSB/JKRSMRH/SEMALATONG/2025/077Proposed Borrow Pit - Simunjan11/11/2025No objection
33PTSB/JKRSMRH/SEMALATONG/2025/078Submission of Concrete Mix Design Grade 40P Hai Shoon Concrete (Serian)11/11/2025No objection
34PTSB/JKRSMRH/SEMALATONG/2025/083Proposed Subgrade Material (Sand) for CH 23+200 to CH 24+20024/11/2025No objection
35PTSB/JKRSMRH/SEMALATONG/2025/086Test Report for Tensile and Slip Test of Reinforcement Couplers25/11/2025No objection
36PTSB/JKRSMRH/SEMALATONG/2025/087Tensile Test Report for Reinforcement Bar T16 & T108/12/2025No objection
37PTSB/JKRSMRH/SEMALATONG/2025/090Proposed Borrow Pit - Semalatong Simunjan8/12/2025No objection
38PTSB/JKRSMRH/SEMALATONG/2025/091Utilization of 75mm DCR as Replacement of Earth Material19/12/2025Resubmission through letter (2026/022)
39PTSB/JKRSMRH/SEMALATONG/2025/092Proposed Borrow Pit at Semalatong30/12/2025No objection
40PTSB/JKRSMRH/SEMALATONG/2026/011Concrete Mixed Design ICE Concrete9/03/2026No objection
41PTSB/JKRSMRH/SEMALATONG/2026/014Revised Concrete Mixed Design Hai Shoon Concrete17/03/2026No objection
42PTSB/JKRSMRH/SEMALATONG/2026/021RC Pile from Iprotech Company24/04/2026with comment, not approved
43PTSB/JKRSMRH/SEMALATONG/2026/022Utilization of 75mm DCR as Replacement of Earth Material6/05/2026No objection
44PTSB/JKRSMRH/SEMALATONG/2026/029Submission Of Tensile Test Report for T12 and T1612/06/2026No objection
45PTSB/JKRSMRH/SEMALATONG/2026/034Submission of Proposed Concrete Mix Design from Hailek Concrete23/07/2026No objection
2.3 METHOD STATEMENT

Method statement approval

At Code 1 (approved)
29 / 29
cumulative, as of 25 October 2026
New submissions
0Aug '26
0Sep '26
0Oct '26
Under review
0
Code 2 · resubmit
0
Code 3 · not approved
0
Omitted / cancelled
0

CODE 1 Approved CODE 2 Commented, resubmit CODE 3 Not approved, resubmit
Major works must be at Code 1 before work proceeds on site.

Method statement register (29 items)
Swipe the table sideways to see all columns.
No.Reference No.DescriptionDate RepliedStatus / Remarks / Action
1PTSB/JKRSMRH/SEMALATONG/2024/004Installation of Prefabricated Vertical Drain29/02/2024No objection, with comment
2PTSB/JKRSMRH/SEMALATONG/2024/010Site Clearing Work7/03/2024No objection
3Earthwork
4Sandfill Work
5Geotextile Laying Work
6Subbase & Roadbase Laying
7PTSB/JKRSMRH/SEMALATONG/2024/021MOS for Piling Works (250mmx250mm RCSQ Pile & 600mm Dia. Spun Pile)17/05/2024No objection
8PTSB/JKRSMRH/SEMALATONG/2024/036Installation of HDPE Pipe Culvert6/08/2024No objection, with comment
9PTSB/JKRSMRH/SEMALATONG/2024/044MOS for Dynamic Pile Load Test (PDA)16/08/2024No objection
10PTSB/JKRSMRH/SEMALATONG/2024/048MOS for Maintained Load Test (MLT)29/08/2024Resubmission through letter (052)
11PTSB/JKRSMRH/SEMALATONG/2024/052Resubmission of MLT (Spun Pile)12/09/2024Resubmission through letter (060)
12PTSB/JKRSMRH/SEMALATONG/2024/052Endorsed Kentledge Setting Up Calculation (Spun Pile)12/09/2024Resubmission through letter (064)
13PTSB/JKRSMRH/SEMALATONG/2024/060Resubmission of MLT (Spun Pile)14/10/2024Resubmission through letter (064)
14PTSB/JKRSMRH/SEMALATONG/2024/063Proposed Replacement of Damaged Driven Test Pile (Spun Pile)24/10/2024No objection
15PTSB/JKRSMRH/SEMALATONG/2024/064Resubmission Endorsed Kentledge Setting Out Calculation (Spun Pile)25/10/2024Resubmission through letter (077)
16PTSB/JKRSMRH/SEMALATONG/2024/070Method Statement for MLT - Binareich Lab & Test S/B14/11/2024No objection
17PTSB/JKRSMRH/SEMALATONG/2024/071MOS for High Strain Dynamic Pile Testing - Binareich15/11/2024No objection
18PTSB/JKRSMRH/SEMALATONG/2024/076Method Statement for Pile Embankment Slab20/11/2024No objection
19PTSB/JKRSMRH/SEMALATONG/2024/077Revised Piling Staging Analysis Report20/11/2024No objection
20Letter of Undertaking for Temporary Piling Staging Design20/11/2024No objection
21PTSB/JKRSMRH/SEMALATONG/2025/006Method Statement for Topping up of Existing Road to Subbase Level26/02/2025Resubmission through letter (2025/040)
22PTSB/JKRSMRH/SEMALATONG/2025/040Method Statement for Topping up of Existing Road to Subbase Level at CH9+000 - CH10+00030/07/2025No objection, with comment
23PTSB/JKRSMRH/SEMALATONG/2025/041Method Statement for the Casting of Post Tension Beams6/08/2025Resubmission through letter (2025/076)
24PTSB/JKRSMRH/SEMALATONG/2025/059Method of Statement for Abutment Construction26/09/2025No objection
25PTSB/JKRSMRH/SEMALATONG/2025/060MOS - Embankment Fill to Surcharge Level using DCR (CH5+400 - CH9+000)26/09/2025No objection, with comment
26PTSB/JKRSMRH/SEMALATONG/2025/076MOS - Casting Post Tensioned Beams (Calculation Existing Piled Embankment)17/10/2025No objection
27PTSB/JKRSMRH/SEMALATONG/2025/082Temporary Crossing at Sg. Spaoh24/11/2025No objection, with comment
28PTSB/JKRSMRH/SEMALATONG/2025/090Method Statement for Rectification of Under Strength Concrete19/12/2025Resubmission through letter (2026/032)
29PTSB/JKRSMRH/SEMALATONG/2026/032Submission Of Revised Method Statement for Under-Strength Concrete9/07/2026No objection
2.4 NON-CONFORMANCE

All 6 NCRs closed

Open NCRs
0
Issued / closed
6 / 6
NCR issued
0Aug '26
0Sep '26
0Oct '26
NCR 001 13 Sep 2024

Settlement gauges not installed (CH1+700 – CH13+800)

CLOSED
NCR 002 13 Sep 2024

Field density tests not carried out on embankment fill layers

CLOSED
NCR 003 20 Jan 2025

G40N concrete below required 28-day strength

CLOSED
NCR 004 27 Jan 2025

Pile protrusion and lean concrete not to drawing

CLOSED
NCR 005 22 May 2025

Earth fill material not complying with gradation limits

CLOSED
NCR 006 24 Sep 2025

Embankment filling (CH19+125 – CH19+425) without prior S.O. approval

CLOSED
NCR register (full text)
NCR/PTSB/B084/001Close
Date issued
13/09/2024
Received by
Loh Cheng Yong
Closed out
TBA

The Contractor has not installed the rod settlement gauge between CH1+700 - CH13+800 (refer attachment 1.0). Installation of settlement gauge is compulsory as referred to Specifications of Particular Application [Part 3 (i)(b)]; Section 8; Sub-Section 6.2;"Settlement Gauges" & construction drawing no. PTSB/SMLT/ST/01 & 05 for detailed settlement monitoring purposes.

Corrective action by contractor
Due date: –
Proposal: The remaining settlement gauge will be installed continously for other required chainage.
NCR/PTSB/B084/002Close
Date issued
13/09/2024
Received by
Loh Cheng Yong
Closed out
10/11/2024

The Contractor has not conducted the soil Field Density Test for road embankment, between CH0+700 - CH2+000 & CH7+300 - CH7+500 respectively, for ongoing road embankment earth filling works (refer attachment 1.0). Soil Field Density Test shall be conducted for each compacted layer before proceeding the next stages of works, as referred to the Standard Specification For Road Works (JKR/SPJ/2013-S2); Section 2.2; Sub-Section 2.2.4.4;"Compaction".

Corrective action by contractor
Due date: –
Proposal: The pending FDT will be conducted concurrently for each 300mm layer of soil embankment.
NCR/PTSB/B084/003Close
Date issued
20/01/2025
Received by
Loh Cheng Yong
Closed out
TBA

The contractor did not meet the required design strength (40 N/mm²) and target mean strength (47.38 N/mm²) for the G40N concrete grade in the 28-day cube compressive test. The average result was only 38.3 N/mm², with individual values of 34.7, 52.9, and 27.4 N/mm² for the 3 samples. (refer attachment 1.0 & 2.0)

Thus, the contractor must propose and submit a rectification works, endorsed by a Professional Engineer with Practicing Certificates, to the Superintending Officer for review and consideration before proceeding with the next stage of work.

The contractor is reminded to ensure that all concrete materials delivered to the site comply with the construction drawing, contract specifications (JKR/SPJ/2009-S9), and approved design mix.

Corrective action by contractor
Due date: –
Proposal: –
NCR/PTSB/B084/004Close
Date issued
27/01/2025
Received by
Loh Cheng Yong
Closed out
26/02/2025

The contractor failed to provide the protuded 75mm length (from the cut-off level to the top surface of the lean concrete) for the exposed RC pile head. Additionally, the constructed lean concrete was found to be damaged. (Refer attachment 1.0)

Thus, the contractor must propose and submit a rectification works, endorsed by a Professional Engineer with Practicing Certificates, to the Superintending Officer for review and consideration before proceeding with the next stage of work.

The contractor is reminded to ensure that all construction materials delivered to the site comply with the construction drawing and contract specifications (JKR/SPJ/2008-S9) accordingly.

Corrective action by contractor
Due date: –
Proposal: To remove & reconstruct the lean concrete as per construction drawing & contract specifications accordingly.
NCR/PTSB/B084/005Close
Date issued
22/05/2025
Received by
Loh Cheng Yong
Closed out
21/10/2025

Referring to your letter (GASB/JKR/GDSM/L138) & our letter (PTSB/JKRSMRH/SEMALATONG/2025/023), it was found out that the test results of the gradation limit is not comply with the specifications. Furthermore, these materials were delivered and placed on the existing plantation roads as part of the embankment fill for the proposed road alignment before the official test results were received as proposed by the contractor. (Refer to Site Memo No. 22)

This issue must be addressed as a priority. Please carry out all necessary corrective actions and ensure they are completed within 14 days from the date of this notice.

Kindly be reminded that the Method Statement and Material submission must be approved prior to proceeding with the next stage of the work.

Corrective action by contractor
Due date: –
Proposal: New samples has been taken for testing at approved accredited laboratory.
NCR/PTSB/B084/006Close
Date issued
24/09/2025
Received by
Loh Cheng Yong
Closed out
TBA

It has come to our attention that earth filling works for the road embankment between CH19+425 and CH19+125 have been carried out without prior approval from Superintending Officer. (refer attachment 1.0)

Kindly take note of the following comments and observations:

1. Submission of locality plan and permit for the borrow pit is still pending.

2. Suitability test results for the borrow pit material have not yet been submitted.

3. Approval Chit for the backfilling activity is pending.

4. Drainage layer provided prior to backfilling is of insufficient width.

Please be reminded that it is the contractor's sole responsibility to ensure that all materials used and works executed are in full compliance with the approved contract specifications and construction drawings. Failure to comply with the above requirements shall be deemed as carrying out unauthorized works. The contractor will bear full responsibility for the consequences of such actions, including but not limited to any liabilities, defects, or claims that may arise.

Implementation of appropriate rectification measures shall be carried out without delay.

Corrective action by contractor
Due date: –
Proposal: –
2.5 SITE MEMOS

Site memos

Issued (cumulative)
42
Open / closed
1 / 41
Site memos issued
0Aug '26
2Sep '26
1Oct '26

Works already behind schedule

Site Memo SM/PTSB/B084/042 · Delay Notification of Work Progress · issued 21/10/2026
Based on site progress as at 21/10/2026 against the Revised Work Programme Rev.01 (Ref.: L286), the following works have fallen behind schedule:

a
Sg. Simunjan Kanan Bridge

Piling works for Embankment B (scheduled to start 06/03/2026) and Abutment B (scheduled to start 15/09/2026) have yet to commence.

CRITICAL PATH
b
Earthworks Ch 14+876 – Ch 18+400

Settlement gauge, free drainage layer, embankment fill and surcharge works have yet to commence. The surcharge period was scheduled to start 25/07/2026.

CRITICAL PATH
c
Sg. Spaoh Bridge

Piling works for Embankment A (scheduled to start 22/05/2026) have yet to commence; slab concreting for Embankment B (scheduled to complete 25/04/2026) is only about 50% completed.

BEHIND SCHEDULE
KEY POINT
Items (a) and (b) are on the critical path and, if not recovered, will affect the completion of the Works.

Latest site memos

SM/037 17/12/2025

Laying of DCR over Surcharge Layer from Ch 0+000 to Ch 0+600

SM/038 20/02/2026

Notification of Compressive Strength of 31 days for Concrete Grade 40P

SM/039 25/03/2026

Earth Embankment Works

SM/040 10/08/2026

Notification of Compressive Strength of 11 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)

SM/041 10/08/2026

Notification of Compressive Strength of 10 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)

SM/042 21/10/2026

Delay Notification of Work Progress

Site memo register (42 memos)
Swipe the table sideways to see all columns.
No.Ref. NoDescriptionDate IssuedStatusRemarks
1SM/PTSB/B084/001General Reminder - Installation of Road Settlement Gauge26/06/2024Close
2SM/PTSB/B084/002General Reminder - Submission of Soil Test Report for Bukit Lebor & Bukit Entengan Borrow Pit27/06/2024Close
3SM/PTSB/B084/003General Reminder - Installation of Traffic Signages27/06/2024Close
4SM/PTSB/B084/004General Reminder - Implementation of Field Density Testing4/07/2024Close
5SM/PTSB/B084/005General Reminder - Submission of Temporary Works (Staging System) at Sg. Simunjan Kanan River Bank.18/07/2024Close
6SM/PTSB/B084/006General Reminder - Provision of Site Office Facilities.18/07/2024Close
7SM/PTSB/B084/007General Reminder - Submission of Approval Chit Form (Period of July 2024).24/07/2024Close
8SM/PTSB/B084/008General Reminder - Reinstatement of Damage/Missing Rod Settlement Gauge.24/07/2024Close
9SM/PTSB/B084/009General Reminder - Sequence Of Work For Pipe Culvert Construction.30/07/2024Close
10SM/PTSB/B084/010Placement of Unrelated Construction Materials.6/09/2024Close
11SM/PTSB/B084/011Routine Testing for Geotextiles6/09/2024Close
12SM/PTSB/B084/012Damage of Geotextiles19/09/2024Close
13SM/PTSB/B084/013Piling Works (Test Pile) for 600mm Dia. Spun Pile3/10/2024Close
14SM/PTSB/B084/014Unset Piling Works (Test Pile) RC.SQ Pile 250mm3/10/2024Close
15SM/PTSB/B084/015Placement of Temporary Road Barrier7/10/2024Close
16SM/PTSB/B084/016Unset Piling Point - Sg. Simunjan Kanan Bridge Embankment A5/11/2024Close
17SM/PTSB/B084/017Notification of Compressive Strength of 7 days for Concrete Grade 4031/12/2024Close
18SM/PTSB/B084/018Notification of Compressive Strength of 7 days for Concrete Grade 406/01/2025Close
19SM/PTSB/B084/019Insufficient of Road Formation Width15/01/2025Close
20SM/PTSB/B084/020Removal of Blockstone & Replacement With Suitable Materials14/02/2025Close
21SM/PTSB/B084/021Replacement of Soil Materials with DCR 3" for Road Embankment14/05/2025Close
22SM/PTSB/B084/022Slow Progress on Site15/05/2025Close
23SM/PTSB/B084/023Surcharge Works1/07/2025Close
24SM/PTSB/B084/024Insufficient Road Embankment Width (CH4+000 - CH5+700)21/07/2025Close
25SM/PTSB/B084/025Submission of Approval Chit Form (Period of July 2025)24/07/2025Close
26SM/PTSB/B084/026Fabrication of Bridge Girder Beam25/07/2025Close
27SM/PTSB/B084/027Settlement Monitoring Works11/08/2025Close
28SM/PTSB/B084/028Replacement of Soil Materials with DCR 3" for Road Embankment22/08/2025Close
29SM/PTSB/B084/029Notification of Compressive Strength of 28 days for Concrete Grade 40N20/10/2025Close
30SM/PTSB/B084/030Notification of Compressive Strength of 28 days for Concrete Grade 50P20/10/2025Close
31SM/PTSB/B084/031Temporary River Crossing at Sg. Spaoh30/10/2025Close
32SM/PTSB/B084/032Reminder on Mandatory Use of Personal Protective Equipment (PPE) On Site18/11/2025Close
33SM/PTSB/B084/033Damages Of Girder Beam No. 1 Type 40 (Flange) Sg. Simunjan Kanan Bridge5/12/2025Close
34SM/PTSB/B084/034Notification of Compressive Strength of 29 days for Concrete Grade 50P (Type16 Girder Beam No. 2, Sg. Simunjan Kanan Bridge)6/12/2025Close
35SM/PTSB/B084/035Notification of Compressive Strength of 7 days for Concrete Grade 40 (Pile Cap Pier 1 & Abutment Headwall Sg. Simunjan Kanan Bridge)10/12/2025Close
36SM/PTSB/B084/036Notification of Compressive Strength of 28 days for Concrete Grade 40P16/12/2025Close
37SM/PTSB/B084/037Laying of DCR over Surcharge Layer from Ch 0+000 to Ch 0+60017/12/2025Close
38SM/PTSB/B084/038Notification of Compressive Strength of 31 days for Concrete Grade 40P20/02/2026CloseHai Soon Concrete
39SM/PTSB/B084/039Earth Embankment Works25/03/2026Close
40SM/PTSB/B084/040Notification of Compressive Strength of 11 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)10/08/2026CloseHai Soon Concrete
41SM/PTSB/B084/041Notification of Compressive Strength of 10 days for Concrete Grade 40 (Embankment B Sg. Spaoh bridge)10/08/2026CloseHai Soon Concrete
42SM/PTSB/B084/042Delay Notification of Work Progress21/10/2026Open
2.6 REQUESTS FOR INFORMATION

No RFIs or site queries this period

Issued
0
Under review
0
Closed
0
RFI issued
0Aug '26
0Sep '26
0Oct '26

Site queries under review: nil for the reporting period 26-09-2026 to 25-10-2026.

2.7 TESTING

1,783 tests passed to date

Passed
1,783
Failed
43
Retest
5
Total
1,831

Tests per month

Aug '26
103
Sep '26
76
Oct '26
0
Remarks
  • 5 nos. of Field Density Test have been retested.
  • Cumulative failed results cover: Field Density Test, cube test, PDA RCSQ pile (250 mm), PDA spun pile (600 mm dia.), rebound hammer test and aggregate test (DCR 3").

Tests by type (cumulative)

Cube Test
1,047
Field Density (Soil)
643
Field Density Test (DCR)
42
Pile Test for 250mm RCSQ Pile (PDA)
29
Pile Test 600mm Dia. Spun Pile (PDA)
26
Rebound Hammer Test
9
Borrow Pit Test
8
Rebar Test
7
Pile Integrity Testing (PIT)
4
Aggregate Test DCR 3"
4
Pile Test 250mm RCSQ Pile (MLT)
3
Pile Test 600mm Dia. Spun Pile (MLT)
2
Dipping test (Subgrade)
1
Up to Sep '26Oct '26
Test record by type
Swipe the table sideways to see all columns.
No.DescriptionPrevious MonthOct '26Total
1Cube Test1,04701,047
2Field Density Test (DCR)42042
3Field Density (Soil)6430643
4Field Density Test (Existing)000
5Rebar Test707
6Premix Test000
7Borrow Pit Test808
8Pile Test for 250mm RCSQ Pile (PDA)29029
9Pile Test 250mm RCSQ Pile (MLT)303
10Pile Test 600mm Dia. Spun Pile (PDA)26026
11Pile Test 600mm Dia. Spun Pile (MLT)202
12Pile Integrity Testing (PIT)404
13Rebound Hammer Test909
14Dipping test (Subgrade)101
15Aggregate Test DCR 3"404
Total1,82501,825

Cube testing — pile embankment B, Sg. Spaoh

Photo 1 · 29-day cube test, pile embankment B @ Sg. Spaoh (G/L A–H / 11–15)
Photo 1 · 29-day cube test, pile embankment B @ Sg. Spaoh (G/L A–H / 11–15)
Photo 2 · 29-day cube test result, pile embankment B @ Sg. Spaoh
Photo 2 · 29-day cube test result, pile embankment B @ Sg. Spaoh

Field density testing — earth embankment fill

Photo 3 · Field density test, earth embankment fill @ CH21+925
Photo 3 · Field density test, earth embankment fill @ CH21+925
Photo 4 · Field density test, earth embankment fill @ CH23+175
Photo 4 · Field density test, earth embankment fill @ CH23+175
SITE PROGRESS

26 km Gedong – Semalatong: site progress video

Video to be inserted

Thank you

Questions & discussion

IMPLEMENTING AGENCYJabatan Kerja Raya SarawakWisma Saberkas, Jalan Tun Abang Haji Openg, 93582 Kuching, Sarawak
CONSULTANTPerunding Timur (S) Sdn Bhd4th & 5th Floor "Stallion", Sublot 17, Rock Commercial Centre, 1½ Mile, Jalan Rock, 93200 Kuching, Sarawak

PTSB · QA/QC Monthly Report No. 33 · PWD/HO/B084/2023